Builder punch list template: running the pre-delivery walkthrough

Updated November 9, 2026 · Written for home builders

A builder punch list is the numbered record, made during the pre-delivery walkthrough, of every item still to finish or fix before or soon after closing, with the room, what is wrong, who will fix it, the target date and a sign-off when it is done.

Most punch list templates are written for the buyer

Search for a new home punch list and most of what comes up is written for buyers: bring painter's tape, bring a flashlight, do not let the builder rush you. That is fair advice for them. The builder's job is different. You are running the walk, you own the list afterward, and the list becomes part of the record of what was open on the day the keys changed hands.

This guide is the builder's side: how to run the walkthrough, what each line of the list needs, and how to close it out so the same items do not come back as warranty arguments.

Before the walkthrough

  • Walk it yourself first. The superintendent does an internal walk and fixes what they can, so the buyer's walk is about the small things, not a missing light fixture.
  • Clean the home. Dust and construction debris hide scratches and make finished work look unfinished.
  • Turn everything on. Power, water, gas, heating and cooling, and every appliance, so they can be shown working.
  • Have the paperwork ready. The punch list form, the selections sheet for that home, and the handoff kit pages you plan to show: shutoffs, appliances, the warranty summary and how to ask for a repair.
  • Agree how items get marked. Some builders let buyers place blue tape. Others prefer a photo and a numbered line only. Decide your rule and tell the buyer before the walk.

What to check, room by room

Walk in the same order every time, so nothing gets skipped and every list reads the same way at the office.

AreaWhat to check together
ExteriorSiding, trim, paint, roof edges, gutters and downspouts, grading away from the house, walks and driveway, hose bibs, exterior lights.
GarageDoor and opener, safety sensors, remotes, slab, walls, the door into the house.
Doors and windowsOpen, close and lock each one. Screens present, glass clean and unscratched, weatherstripping in place.
KitchenCabinet doors and drawers, counters and seams, backsplash, sink and faucet, disposal, every appliance running.
BathroomsFixtures and drains, toilets, caulk and grout lines, tile, mirrors, exhaust fans, hot water at each tap.
Walls, ceilings, floorsPaint touch-ups, drywall marks, nail pops, flooring scratches or gaps, stairs and railings.
ElectricalSwitches, outlets, GFCI test and reset buttons, light fixtures, the panel labels.
Heating and coolingSystem runs, the thermostat works, air comes from each vent, the filter is in place.
Plumbing and water heaterNo drips under sinks, water heater running, shutoffs reachable.
SafetySmoke and carbon monoxide alarms tested.

The walkthrough is also the best moment to show the owner each shutoff in person. Our shutoff locations guide covers what to point out and photograph.

The columns every punch list item needs

ColumnWhy it matters
Item numberSo everyone can say "item 4" on the phone and mean the same thing.
Room and exact spot"Hall bath, tub to tile joint, left end" gets fixed. "Bathroom caulk" gets argued about.
What to finish or fixWrite the fix, not just the flaw: "recaulk tub to tile joint", not "caulk bad".
PhotoA photo of each item settles what was there on the day.
ResponsibleYour crew or a named trade. One owner per item.
Target dateA real date the owner can hold you to.
Done and initialsWho fixed it and when, checked by someone other than the person who did the work if you can.

See it filled in for a made-up builder: the sample walkthrough and punch list, or open the blank punch list page to print.

Split the list: before closing, after closing, and warranty

Not every item can be fixed before closing, and not every concern belongs on the punch list. Sorting them on the day prevents most of the friction later.

  • Before closing. Quick cosmetic fixes your own crew can finish: touch-ups, adjustments, a missing screen.
  • After closing, on the list. Items that need a trade or a part on order. They stay on the punch list with a date, and you track them, not the owner.
  • Warranty items. Anything noticed after the walkthrough goes through your warranty process. Say so on the form, and point to the page in the kit that explains how to ask for a repair.
  • Not agreed. If you and the buyer disagree on an item, write it down anyway and mark it as not agreed. A clear record is better than a silent one.

Sign-off and close-out

  1. Read the open items back to the buyer before anyone signs.
  2. Both buyers and your representative sign and date the list.
  3. Give the buyer a copy the same day, printed or as a PDF.
  4. Book the re-walk or follow-up visit for the open items.
  5. When each item is done, mark it with the date and initials. Send the owner the closed list once everything is done.
  6. File the signed list in the home's handoff kit, behind the warranty pages, so it is easy to find in the first year.

The punch list page is already in the kit

Builder Handoff Kits includes a two-sheet walkthrough checklist and punch list with your logo, item columns, photo spots and signature lines, plus a note that later items follow your warranty process. Ordering opens soon.

See what the kit includes

Common mistakes

  • Vague lines like "fix paint" with no room or spot.
  • Items with no owner and no date, so they drift for weeks.
  • Letting the walkthrough become a warranty negotiation. Note the concern, sort it, and move on.
  • Never sending the owner the closed list, so they cannot tell what was finished.
  • Keeping the only copy in the superintendent's truck.

Questions builders ask

What is a builder punch list?

It is the numbered list, made during the pre-delivery walkthrough, of every item still to finish or fix, with the room and spot, the fix, who is responsible, a target date and a sign-off when it is done.

Is a pre-delivery inspection the same as a punch list walkthrough?

Builders use both names for the walk before closing. The inspection is the walk itself; the punch list is the written record of what it found.

What columns should a punch list template have?

Item number, room and exact spot, what to finish or fix, a photo, who is responsible, a target date, and a done date with initials.

What happens to problems found after the walkthrough?

They go through the builder's warranty process. The punch list form should say so and point to the page that explains how to ask for a repair.