We walk the home together before closing. We note anything to finish or fix, and agree on when it will be done.
Home: 142 Sample Creek Way, Anytown, USA. Lot: 27. Community: Sample Creek. Inspection date: March 13, 2026. Builder rep: Sam Ortiz.
| Area | Checked | Notes |
|---|---|---|
| Exterior: siding, trim, paint, gutters | Yes | Touch up trim at garage corner |
| Driveway, walks, grading, landscape | Yes | OK |
| Garage and garage door | Yes | OK |
| Entry and doors (open, close, lock) | Yes | Back door sticks slightly |
| Windows (open, close, lock, screens) | Yes | Screen missing, bedroom 3 |
| Kitchen: cabinets, counters, appliances | Yes | Adjust pantry door |
| Bathrooms: fixtures, tile, caulk, fans | Yes | Caulk gap at tub, hall bath |
| Floors and stairs | Yes | OK |
| Walls, ceilings, paint | Yes | Scuff in hallway |
| Lights, switches, outlets | Yes | OK |
| Heating and cooling run | Yes | OK |
| Water heater and plumbing | Yes | OK |
| Smoke and CO alarms | Yes | All tested |
| # | Room / location | Item to finish or fix | Responsible | Target date | Done (initials) |
|---|---|---|---|---|---|
| 1 | Garage, exterior corner | Touch up trim paint | Paint trade | Mar 18, 2026 | SO |
| 2 | Back door | Adjust strike so door closes easily | Builder | Mar 18, 2026 | SO |
| 3 | Bedroom 3 | Install missing window screen | Window supplier | Mar 19, 2026 | SO |
| 4 | Kitchen pantry | Adjust door hinges | Builder | Mar 18, 2026 | SO |
| 5 | Hall bath | Recaulk tub to tile joint | Tile trade | Mar 19, 2026 | SO |
| 6 | Hallway | Touch up wall scuff | Paint trade | Mar 18, 2026 | SO |